Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Placing New Sonotube Footing Next to Existing Footing

Status
Not open for further replies.

mattradk

Civil/Environmental
Jul 23, 2016
22
I've been asked to design a 12'x15' deck in upstate New York. It would be placed with the ledger (long side) against the back of the house and the shorter side against a sunroom that's 12' deep and 15' wide. So, it's intended to go in an inner corner of the home footprint. The home (and fill) is about a year old. The fill is clean material with a large sand component.

The deck would be a conventional design with a beam (3-2x10's) running parallel to the house supporting the 2x8 joists which would have a 19" cantilever. The 12' side of the deck would be placed along the sunroom. The deck beam would be supported by three piers placed on 16" footings, 48" deep placed in sonotubes. The distance from the top of the footings to the bottom of the beam would be around 4-1/2'.

The problem I'm looking at is that the end pier and the 16" footing of the deck would need to be placed around 12" from the existing 18" sunroom footing. I'm concerned that digging the hole for the 16" deck footing would threaten the close-by 18" footing of the sunroom. Maybe it could shift toward the hole made for the 16" deck footing, or even buckle at the point where the pier meets the footing at ground level?

The attached photo shows the sunroom and its piers. The deck would be placed to the left of the sunroom in the photo where the stairs are visible.

Does anyone have a sense if placing the new 16" footing (along with the need to hand-excavate for it) would be a problem for the sunroom footing?

If so, any idea how much of a separation between the deck and sunroom footing would be reasonably safe? I've already allowed for a cantilever of the beam to move the footing away from the sunroom as far as possible.

I could conceivably have the contractor stabilize the sunroom pier in question by placing a 2x8 across the bottom of all three sunroom piers while construction is ongoing, and direct him to compact the fill around the sonotube for the 16" deck footing sonotube before and after filling them with concrete. The 2x8 would hold the sunroom footing in place while the potential threat exists.

Thanks!
 
 https://files.engineering.com/getfile.aspx?folder=41b22b79-bd10-431f-824a-0cee64b4134c&file=Sunroom_Piers.jpg
Replies continue below

Recommended for you

This posting was a relatively long one because I figured I might get questions. The short version is: Can a new sonotube-type 48" deep footing for a deck be placed close (a foot of so) to an existing, heavily loaded footing?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor