Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Post tensioned slab on grade demolition

Status
Not open for further replies.

clark1007

Structural
Jan 3, 2003
2
I need to trench through an existing post tensioned slab on grade here in Texas. My opiniion is to relax the tendons in the area and retension afterwards. Any helpful hints would be greatly appreciated. Thanks!!!
 
Replies continue below

Recommended for you

Is the proposed trenching full depth? and over a large area?

If you destress the tendons you will have to use special stressing gear to re-stress.

I would try and do localised trenching without destressing, maybe consider staging the trenching and re-patching, if possible. Really depends on the dimensions you are proposing for the trenching.

The trenching should be at least 36" from any anchorages to avoid a potential anchorage failure etc.

HTH





 
The trenches are full depth and long lengths...the need to move kitchen plumbing to different area in the building. After de-stressing and the cable are cut, can I re-anchor the cables and re-stress, or is there another method. Also, the areas that don't have post tensioning, should I heavily conventionally reinforce? This is a bit out of my experience, but a project that needs addressing, nonetheless.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor