mijowe
Structural
- Feb 3, 2003
- 204
We have a project where we are taking out a column in a steel office building and supporting it with two new transfer beams supported by two new columns. We have an engineer in the office who likes to pre-load the beam for dead load in these situations (sit the beam in place, jack up the supports until the beam deflects the calculated dead load deflection, then lock it into place) This, in theory, eliminates any settlement at the transfer and in turn any possible damage to finishes above. The other option would be to size the beams to limit deflection, likely getting beam sizes significantly larger than if they were preloaded.
Do people like either of the two options above better, and what are your brief reasons?
Do people like either of the two options above better, and what are your brief reasons?