Got an ASME VIII D1/NBIC Question. So, my engineers forgot to send out updated mechanical calculations, or to update the hydro test pressure in the drawings. The equipment was fabricated per the new calcs (material thicknesses and such), but hydro tested to the old values, which was a much lower pressure (about 70% of required). The equipment has already shipped to the customer. The question is, can we submit an R-2 to cover the new calcs and have an R-stamp shop perform the hydro at the higher pressure? Or do I need to get the equipment shipped back to the shop and reperform the hydro and write up a new U-1? The equipment has not yet been placed in service. Thanks in advance!
-Willy