cjkelly83
Structural
- Jun 28, 2016
- 8
I have a connection design which is effectively a beam with welded end plate connecting to a column column by a 4 bolt group which is set within the beam flanges.
I have two questions relating to prying in this connection.
1 - Do I have to consider prying of the end plate?
2 - If I add full depth web stiffeners to the column do i still check it for prying and if so how?
From the literature I've read it only takes account of unstiffened flanges and makes no comment on stiffened flanges.
I have two questions relating to prying in this connection.
1 - Do I have to consider prying of the end plate?
2 - If I add full depth web stiffeners to the column do i still check it for prying and if so how?
From the literature I've read it only takes account of unstiffened flanges and makes no comment on stiffened flanges.