gordini
Civil/Environmental
- Aug 22, 2005
- 1
This is a challenge to me because this is my first pump station design, however I'm sure that this has occured once or twice before to somebody. OK, here it is:
I have a package pump station design with a peak operating flow of about 250 gal/min. The force main (4" dia.) discharges into an existing gravity main (10" dia.) about 1400' feet away. My problem is that there is an elevation peak in the line occuring midway that is about 30' higher than the pump station and gravity connection.
As far as I can tell, I have three options:
Option 1 is to terminate the force main at the peak and install a manhole connection. From there I could run a gravity line and tie into the existing gravity main. The problem with this is that it will be more expensive. It requires a deeper excavation (10'-15') to ensure service for any other properties that may want to connect to it in the future.
Option 2 is to install the 4" force main all the way down to the gravity connection, install an air release valve, and just let the last part of the line function as a gravity line during the pump off cycle. This is proably the most economical solution except for I don't know if this will cause any corrosion or pipe cleaning problems.
Option 3 is to install the 4" force main all the way down to the gravity connection, install some type of spring-loaded valve at the end that would close during the pump off cycle and then reopen during the pump on cycle. This way, the line always stays full until the pipe discharges. The only problem is that I do not know if there is a mechanical valve available for this type of application. Also, I'm sure that a larger pump is required for this since I would be inducing a restriction at the end of the line.
Any comments / suggestions on which option is best or if there is another option I am not considering?
I have a package pump station design with a peak operating flow of about 250 gal/min. The force main (4" dia.) discharges into an existing gravity main (10" dia.) about 1400' feet away. My problem is that there is an elevation peak in the line occuring midway that is about 30' higher than the pump station and gravity connection.
As far as I can tell, I have three options:
Option 1 is to terminate the force main at the peak and install a manhole connection. From there I could run a gravity line and tie into the existing gravity main. The problem with this is that it will be more expensive. It requires a deeper excavation (10'-15') to ensure service for any other properties that may want to connect to it in the future.
Option 2 is to install the 4" force main all the way down to the gravity connection, install an air release valve, and just let the last part of the line function as a gravity line during the pump off cycle. This is proably the most economical solution except for I don't know if this will cause any corrosion or pipe cleaning problems.
Option 3 is to install the 4" force main all the way down to the gravity connection, install some type of spring-loaded valve at the end that would close during the pump off cycle and then reopen during the pump on cycle. This way, the line always stays full until the pipe discharges. The only problem is that I do not know if there is a mechanical valve available for this type of application. Also, I'm sure that a larger pump is required for this since I would be inducing a restriction at the end of the line.
Any comments / suggestions on which option is best or if there is another option I am not considering?