sta07750
Chemical
- Aug 8, 2012
- 14
I'm spec'ing out a new pump for our waste water lift station. The lift station will pump out via trash pumps through some discharge piping and into a common sewage header that runs to the treatment plant. The issue I'm having is that the common header is filled mostly by a another, larger lift station. That means the common header can be anywhere from 5psig to 25 psig. How can I pipe up these new pumps so that I don't see pump run out when the forced main isn't running at the higher pressure? We need to run these at about 140gpm and 80' TDH (25 feet up and into a 25psig header).
Our previous setup was driven by sewage ejectors and those seemed to work just fine until we ran into compressor reliability problems and check valve problems.
Thanks for any ideas.
Our previous setup was driven by sewage ejectors and those seemed to work just fine until we ran into compressor reliability problems and check valve problems.
Thanks for any ideas.