RememberTheAlamo
Petroleum
- Nov 18, 2008
- 15
Hi All,
Local practices and inventories have driven us to step "out-of-the-box" for sourcing of the plastic chairs, which our mesh should sit on.
Since I am spending $3K for mesh/materials . . . I really want this mesh in the middle of the concrete (not at the bottom).
Unfortunately, neither the W6 mesh nor a sufficient number of plastic chairs are available locally.
So we will be using 8x20 sheets of W4xW4 4x4 mesh and supporting these with 2 1/2" high 4" diameter Schedule 40 pipe sections (a lot of them).
The slab will be 96' by 48', 6" in depth (a little lower around the drains), fiber reinforced 4,000 psi concrete, pumped.
The idea is to cut 40+ 2 1/2" lengths of pipe from a 10' PVC pipe. These would be laid on the vapor barrier and we would then lay the mesh on top of the pipe sections (tying off the sheets).
During the pour, when walking on the mesh, the pipe sections won't collapse like the plastic chairs sometimes do, nor tip over like composite chairs will do. We will still use the plywood "lilly pads" for walking to reduce disruption of the mesh.
This definitely isn't "typical" . . . so I ask the audience your thoughts and recommendations.
The foreman was going to cut bricks to do the same (plastic pipe is way easier to cut and move) . . . and the inspector doesn't want to see those bricks!
So we will end up with around 1600 4" diameter, white plastic 2 1/2 " tall rings supporting the mesh . . . not the greatest solution, but probably better than the promise to "pull the wire up as we go".
Thank you,
Thoughts?
Larry
Local practices and inventories have driven us to step "out-of-the-box" for sourcing of the plastic chairs, which our mesh should sit on.
Since I am spending $3K for mesh/materials . . . I really want this mesh in the middle of the concrete (not at the bottom).
Unfortunately, neither the W6 mesh nor a sufficient number of plastic chairs are available locally.
So we will be using 8x20 sheets of W4xW4 4x4 mesh and supporting these with 2 1/2" high 4" diameter Schedule 40 pipe sections (a lot of them).
The slab will be 96' by 48', 6" in depth (a little lower around the drains), fiber reinforced 4,000 psi concrete, pumped.
The idea is to cut 40+ 2 1/2" lengths of pipe from a 10' PVC pipe. These would be laid on the vapor barrier and we would then lay the mesh on top of the pipe sections (tying off the sheets).
During the pour, when walking on the mesh, the pipe sections won't collapse like the plastic chairs sometimes do, nor tip over like composite chairs will do. We will still use the plywood "lilly pads" for walking to reduce disruption of the mesh.
This definitely isn't "typical" . . . so I ask the audience your thoughts and recommendations.
The foreman was going to cut bricks to do the same (plastic pipe is way easier to cut and move) . . . and the inspector doesn't want to see those bricks!
So we will end up with around 1600 4" diameter, white plastic 2 1/2 " tall rings supporting the mesh . . . not the greatest solution, but probably better than the promise to "pull the wire up as we go".
Thank you,
Thoughts?
Larry