JENGA4
Mechanical
- Nov 20, 2023
- 3
Hello,
I'm new to drafting and am developing some drawing templates for rack elevation diagrams. This may be a dumb question, but I was curious if some flexibility is generally allowed in following the ASME minimum standards if the standards don't make sense with the drawings.
For example, ASME Y14.34M states that a column for Quantity Required is mandatory on the Parts List, but I'm building our parts list for each row to correspond to a rack U elevation, so qty will always be 1 and it won't be helpful to have a column for quantity. Would appreciate any feedback from engineers who have been in the industry longer and have a better understanding of applying standards.
Thanks!
Jenga4
I'm new to drafting and am developing some drawing templates for rack elevation diagrams. This may be a dumb question, but I was curious if some flexibility is generally allowed in following the ASME minimum standards if the standards don't make sense with the drawings.
For example, ASME Y14.34M states that a column for Quantity Required is mandatory on the Parts List, but I'm building our parts list for each row to correspond to a rack U elevation, so qty will always be 1 and it won't be helpful to have a column for quantity. Would appreciate any feedback from engineers who have been in the industry longer and have a better understanding of applying standards.
Thanks!
Jenga4