k3_at_ke
Industrial
- Feb 3, 2023
- 8
Scenario: Taking a subset of welds, hydrotesting them, placing them in service, and then later conducting x-ray examination of a predetermined weld. Is this practice code-compliant according to ASME B31.3?We are the owner-operator and are considering four spools for four different pieces of equipment in our facility. Each spool has five welds. To meet the 5% normal service requirement, we take one of the 20 welds and X-Ray it. However, is it code-compliant if we predetermine that we will X-Ray, say, weld number 17 out of 20, then have the welder weld and complete three of the four jobs—thus 15 welds—and without his knowledge, as he is working on the final spool for the final job (welds 16-20), can we hydrotest the completed three spools and put them in service? Once the last spool is completed, can we take an X-ray of the predetermined weld 17 and still be code-compliant?