arawinda
Structural
- Aug 20, 2015
- 25
In our site, in which still secant pile construction in progress, we experienced concrete had been hardened rapidly (in less than initial setting time) in several piles along the boundary closer to sea. This pile line is about 120m from sea.
Could you please state possible reasons for this and how to solve it?
Please see map attached.
Thanks.