bookowski
Structural
- Aug 29, 2010
- 983
I've looked through some of the past discussions on this topic but didn't find any consensus.
Dealing with renovations of existing rowhouses, single span joists bearing wall to bearing wall. Existing joists are usually 2.75" x 8" to 10" deep spanning around 20ft. Typically the ceilings are down so full access to the joists but they don't want to remove the flooring or existing joist, they also want to avoid new wall pockets. I'm left with reinforcing the existing joists with new members that can go close to the ends of the existing members, but do not have bearing at their ends. Two questions:
1. I've specified this in the past with typical details that have been handed down. I started thinking about the calcs today and I'm not sure if I'm thinking straight. Assume that a new LVL of the same depth is provided at the side of each existing member. The existing floor probably won't directly load the new LVL due to existing deformations/unevenness, so the floor load goes through the existing member. For arguments sake - if I was to through bolt at the center (vertically) of the two members there should be no horizontal shear between the two. However, the members will be forced to have deformation compatibility correct? It seems to me that the majority of the bolting (or nailing/glueing) does not do much, except at the end of the new member. As long as the connection between the two members at the ends can transfer the shear out of the LVL reinforcing back into the existing member I should be ok correct?
2. I get a lot of requests to do the above fix but using a cold formed metal stud attached to the existing joist (lighter, easier to maneuver into an exist. bldg etc). Has anyone done this and can recommend for or against it?
Dealing with renovations of existing rowhouses, single span joists bearing wall to bearing wall. Existing joists are usually 2.75" x 8" to 10" deep spanning around 20ft. Typically the ceilings are down so full access to the joists but they don't want to remove the flooring or existing joist, they also want to avoid new wall pockets. I'm left with reinforcing the existing joists with new members that can go close to the ends of the existing members, but do not have bearing at their ends. Two questions:
1. I've specified this in the past with typical details that have been handed down. I started thinking about the calcs today and I'm not sure if I'm thinking straight. Assume that a new LVL of the same depth is provided at the side of each existing member. The existing floor probably won't directly load the new LVL due to existing deformations/unevenness, so the floor load goes through the existing member. For arguments sake - if I was to through bolt at the center (vertically) of the two members there should be no horizontal shear between the two. However, the members will be forced to have deformation compatibility correct? It seems to me that the majority of the bolting (or nailing/glueing) does not do much, except at the end of the new member. As long as the connection between the two members at the ends can transfer the shear out of the LVL reinforcing back into the existing member I should be ok correct?
2. I get a lot of requests to do the above fix but using a cold formed metal stud attached to the existing joist (lighter, easier to maneuver into an exist. bldg etc). Has anyone done this and can recommend for or against it?