Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Reinforcing Inserts at Construction Joint 1

Status
Not open for further replies.

SperlingPE

Structural
Dec 27, 2002
591
0
0
US
I am designing a concrete slab that will stop short of a complete slab pour due to construction constraints. I am looking for a tube/pipe insert to embed at the edge of the pour. I would like to insert dowels into the tube/pipe when the remainder of the slab is to be poured. I am tryign to avoid casting the dowels in the first pour to avoid them sticking out until the rest of the slab is poured. Does anybody make such an item? Should I just go with a pipe that fits the dowel?
 
Replies continue below

Recommended for you

i've seen the inserts before...not sure what they're called...but they do exist. the ones i saw create the slip joint at the pour back strips for tilt panel warehouses.
 
Status
Not open for further replies.
Back
Top