Would like to know if anybody had to develop plan to address PRD deficiencies?
I am currently working on a list of PSVs with the following deficiencies: incorrect setpoint, Inlet/Outlet Piping issues, orifice/valve sizing issues, oversized, undersized.
The way I thought about prioritizing them was to have the ones in hazardous chemicals on the top of the list, together with the ones that are Safety Critical. The next level should probably be based on cost.
Is there a better approach? Am I in correct the way I am prioritizing them?
Can I have some ideas on how to prioritize the remaining ones?
I am currently working on a list of PSVs with the following deficiencies: incorrect setpoint, Inlet/Outlet Piping issues, orifice/valve sizing issues, oversized, undersized.
The way I thought about prioritizing them was to have the ones in hazardous chemicals on the top of the list, together with the ones that are Safety Critical. The next level should probably be based on cost.
Is there a better approach? Am I in correct the way I am prioritizing them?
Can I have some ideas on how to prioritize the remaining ones?