LittleEd
Mechanical
- Nov 28, 2012
- 28
Large (5" thk) ASME Sect. I Header section (PART). One end of header has TEE on the end, so temporary flat heads were welded-in for hydro testing in shop. After successful hydro test, the temporary flat heads were removed and ID surfaces where temporary weld was removed were examined by MT. A few small linear indications were observed and removed by grinding, MT examined again to verify indication has been removed. I am not sure of depth of areas where indications were removed, expect maybe 3/32" max.
Question: Can the excavated areas be repaired by welding without having to hydro test again? The repaired areas would have final MT examination (same method which found the indications) performed. PW-54 only seems to address repairs found by hydro test, repaired, then rehydro tested (and some exceptions noted in PW-54.3)? This repair doesn't really fit PW-54.3 exceptions.
Since the Header is actually only a segment of the Header, there will be butt-welding and another hydro test performed in field. Due to the thickness of the header and small size and depth of the indications after removal, just seems final MT examination should be sufficient. It seems it would be more detrimental to weld temporary flat heads back in to re-hydro, and have to go through removal process again, all for such minor surface indications after removal of temporary attachment (flat head for hydro test only)?
Other option would be to just "blend-out" excavtions to at least 3:1 taper and MT.
Question: Can the excavated areas be repaired by welding without having to hydro test again? The repaired areas would have final MT examination (same method which found the indications) performed. PW-54 only seems to address repairs found by hydro test, repaired, then rehydro tested (and some exceptions noted in PW-54.3)? This repair doesn't really fit PW-54.3 exceptions.
Since the Header is actually only a segment of the Header, there will be butt-welding and another hydro test performed in field. Due to the thickness of the header and small size and depth of the indications after removal, just seems final MT examination should be sufficient. It seems it would be more detrimental to weld temporary flat heads back in to re-hydro, and have to go through removal process again, all for such minor surface indications after removal of temporary attachment (flat head for hydro test only)?
Other option would be to just "blend-out" excavtions to at least 3:1 taper and MT.