trackman417
Civil/Environmental
- Mar 25, 2019
- 13
Looking for some insight from you guys on this conundrum I'm having.
Currently have a hipped roof that takes the load from a gable roof. The ridge beam at the hip roof is transferred down to 4 hip beams(2 on each end). After it is all said and done, I have about 8000 pounds(pulling from memory here - on vacation, but can't stop thinking about this) of compression being pushed through the hip beams which then dump 6000lb(x and y) at the corners of the load bearing walls.
Original design of the roof assumed that the hip-beams took a couple hundred pounds of compression, not 6000lbs. Looking for some help as I am sure the builder would not like any detail I have to resolve these forces - except for the first option.
Ideas:
1).Assume collar ties will help support ridge board/beam(hip roof is 9.5/12)... Not sure if they would would work with this particular arrangement due to the uneven symmetry.
2). Add 15/32 shear walls on both sides of load bearing walls (3" edge nails, with 6" field nails in these areas)
3). There are some 2X4 partition walls underneath here that I may be able to throw posts down into, but would not like the load path. Could ask the architect to make the room a little smaller to accommodate.
Would appreciate any recommendations/comments.
NOTE: The house is mirrored on the other side
Currently have a hipped roof that takes the load from a gable roof. The ridge beam at the hip roof is transferred down to 4 hip beams(2 on each end). After it is all said and done, I have about 8000 pounds(pulling from memory here - on vacation, but can't stop thinking about this) of compression being pushed through the hip beams which then dump 6000lb(x and y) at the corners of the load bearing walls.
Original design of the roof assumed that the hip-beams took a couple hundred pounds of compression, not 6000lbs. Looking for some help as I am sure the builder would not like any detail I have to resolve these forces - except for the first option.
Ideas:
1).Assume collar ties will help support ridge board/beam(hip roof is 9.5/12)... Not sure if they would would work with this particular arrangement due to the uneven symmetry.
If they would work, would it be safe to assume the valley beams take the load from the whole jack rafter connecting to it with the collar tie arrangement?
I like this idea because it is the SIMPLEST. Also seems like the rafters at the center of the hipped roof would have to do without the collar ties until the valley and ridge beam get farther apart. Would you guys recommend doubling up the collar ties for the first few rafters that can accept the collar ties?
2). Add 15/32 shear walls on both sides of load bearing walls (3" edge nails, with 6" field nails in these areas)
Design connection with 1/8"(or similar)steel plate to connect both hip beams and drag the tension or compression into the top plates(only about 400psi in tension, less in compression).
3). There are some 2X4 partition walls underneath here that I may be able to throw posts down into, but would not like the load path. Could ask the architect to make the room a little smaller to accommodate.
Would appreciate any recommendations/comments.
NOTE: The house is mirrored on the other side