So this is an odd issue, one that only the Gov't could create.
I landed new #12 wire on a terminal block using ring terminals. The terminal blocks were existing equipment and had #6 studs. The ring terminals I used are for 10-12 GA wire and have a #8 hole.
I am being told by the Gov't that this does not meet NEC requirements and that I must redo all of my connections (several hundred) using ring terminals that have a #6 hole.
I have never seen a 10-12GA ring terminal with anything smaller than a #8 hole. The connections are tight and everything fits nicely.
Anyone have any idea if there is a section in NEC that says what I am doing is wrong?
I landed new #12 wire on a terminal block using ring terminals. The terminal blocks were existing equipment and had #6 studs. The ring terminals I used are for 10-12 GA wire and have a #8 hole.
I am being told by the Gov't that this does not meet NEC requirements and that I must redo all of my connections (several hundred) using ring terminals that have a #6 hole.
I have never seen a 10-12GA ring terminal with anything smaller than a #8 hole. The connections are tight and everything fits nicely.
Anyone have any idea if there is a section in NEC that says what I am doing is wrong?