chrisrosebud2001
Structural
- May 19, 2009
- 52
I have a proposed building site that is a reclaimed surface mining area and the building is to be placed on approximately 200 feet of mine spoil fill. The fill has been in place since approximately 1992, so it is expected that most of the soil consolidation has already taken place. However, it is still recommended by the geotechnical report to improve the site bearing conditions using a deep dynamic compaction procedure. Upon completion of this procedure the report recommends that shallow foundations may be used with a net allowable bearing capacity of 2ksf. It is also noted that this procedure will only be able to effectively compact approximately the upper 20’ of the fill material and therefore, significant differential settlements are expected in the fill below. The report suggests that we design for 1½” of differential settlement over 20’. Myself and the architect for this project do not feel that it is likely feasible to design for this amount of settlement. Has anyone dealt with a similar situation in which it was required for the structure to withstand that much settlement or would it be better to improve the soil conditions further?
Thanks in advance for any advice.
Thanks in advance for any advice.