Settlement of Driven Piles

Status
Not open for further replies.

Mudcake

Geotechnical
Jul 11, 2003
6
0
0
US
I have seen engineers using 1% of pile diamater as an estimate for setllement pile when the maximum load (or capacity) is reached. Where did this come from? Any references?
 
Replies continue below

Recommended for you

That actually could be a very small number and sounds like a value of pile shortening when fully loaded. Possibly not considering any toe movement (settlement).
 
I haven't checked it but I suspect that this is a rule of thumb for end bearing piles of a particular type. This would be the elastic shortening of the pile. Please check your sources when dealing with 'rule of thumb'. There is often a good reason but you should know how it is derived. If you don't don't use it.

For your particular case I wouldn't even begin to quess. If the pile was endbearing then you should look at elastic shortening of the pile.

 