zengx
Mechanical
- Apr 8, 2012
- 27
We are Constructing a 230 km buried pipeline. The pipeline is completed and hydrotested.
During the perming, one of the loaders hit the pipe, leaving a severe damage in the pipe, as shown in the attached picture.
I recommended to remove a 2 meters length of the pipe, and weld a new pup piece.
Since the new welds cannot be hydrotested (easily), i recommended to go for both RT (D4 film) and manual shear UT. The RT is to be supervised and interpreted by NDT level 3.
Any suggestions are welcome.
Mohammed Diab.
Inspection Supervisor - Saudi Aramco.
During the perming, one of the loaders hit the pipe, leaving a severe damage in the pipe, as shown in the attached picture.
I recommended to remove a 2 meters length of the pipe, and weld a new pup piece.
Since the new welds cannot be hydrotested (easily), i recommended to go for both RT (D4 film) and manual shear UT. The RT is to be supervised and interpreted by NDT level 3.
Any suggestions are welcome.
Mohammed Diab.
Inspection Supervisor - Saudi Aramco.