kstone
Civil/Environmental
- Nov 6, 2008
- 4
I am a civil/environmental engineer working for a consulting firm. I was recently asked to determine the approximate size of two footing which will be used to support a 15,000 gallon gasoline AST. I recently took the PE exam and participated in a review class offered by ASCE so I had some reference material pertaining to shallow footing design. There is no information available regarding the soil conditions at the site or depth to bedrock or groundwater, so the calculations I was running was basically to get a footing size that was in the ball park. Using some assumptions, I was able to find the allowable net bearing pressure. With a FOS of 3, the bearing capacity I came up with was 3655 pcf (seem reasonable?). The load with a full tank of gas and structural elements to hold the AST came to 4,100 kips and came up with a footing size of 25x25 for the two footings supporting the load. Considering all of that, I have two questions:
1. Does that footing size or anything else I mentioned seem absurd or ball park reasonable? and...
2. How would I determine a reasonable number for the thickness of the footing.
Thanks in advance for any help with this. These numbers aren't being used for the actual design, but are going to be sent to state agencies as ball park assumptions. Since I just studied this stuff in a limited capacity for the PE exam, I am really curious to figure out this stuff.
Thanks...
-Keith
1. Does that footing size or anything else I mentioned seem absurd or ball park reasonable? and...
2. How would I determine a reasonable number for the thickness of the footing.
Thanks in advance for any help with this. These numbers aren't being used for the actual design, but are going to be sent to state agencies as ball park assumptions. Since I just studied this stuff in a limited capacity for the PE exam, I am really curious to figure out this stuff.
Thanks...
-Keith