SteelPE
Structural
- Mar 9, 2006
- 2,743
I am the EOR of a project that is currently in the shop drawing review phase. The project is a design-build contract where the project team was selected by the contractor. I am not working for the architect, I am working for the contractor.
During the shop drawing review process the fabricator began issuing RFI’s for his portion of the project. I did my best to answer the RFI’s but there were some questions that the architect needed to answer (involving dimensions and elevations). I returned the RFI’s to the contractor within a few days.
A few weeks later the fabricator issues a set of E plans for review. I don’t like reviewing shop drawings but I set aside the time to go through them. They were returned to the contractor within a week. These shop drawing contained all of the same questions from the RFI’s and a few more additional questions. I was curious as to why the RFI’s were not incorporated into the drawings. The drawings were returned with a box labeled "reviewed with comments" not revised and resubmit.
Now after I spoke to the fabricator and the contractor, I have determined that the architect never responded to the RFI’s until a week after I reviewed the E plans…. And that the E plans I reviewed was actually the way of the fabricator forcing the answers from the design team. So a whole other set of shop drawing is impending.
How would you handle a situation like this? Would you review the E plans again or just put a big mark on them saying “See previous set”? Would you just invoice for the extra time to review the plans?
During the shop drawing review process the fabricator began issuing RFI’s for his portion of the project. I did my best to answer the RFI’s but there were some questions that the architect needed to answer (involving dimensions and elevations). I returned the RFI’s to the contractor within a few days.
A few weeks later the fabricator issues a set of E plans for review. I don’t like reviewing shop drawings but I set aside the time to go through them. They were returned to the contractor within a week. These shop drawing contained all of the same questions from the RFI’s and a few more additional questions. I was curious as to why the RFI’s were not incorporated into the drawings. The drawings were returned with a box labeled "reviewed with comments" not revised and resubmit.
Now after I spoke to the fabricator and the contractor, I have determined that the architect never responded to the RFI’s until a week after I reviewed the E plans…. And that the E plans I reviewed was actually the way of the fabricator forcing the answers from the design team. So a whole other set of shop drawing is impending.
How would you handle a situation like this? Would you review the E plans again or just put a big mark on them saying “See previous set”? Would you just invoice for the extra time to review the plans?