Sam_89
Chemical
- Feb 11, 2022
- 3
Hi All,
I have an existing PSV installed at site sized for blocked outlet (required flow 364,536 kg/h / rated flow 432,371 kg/h).
The flow rate through my system is now increasing to 561,815 kg/h and hence we will add an additional smaller PSV to cover the extra flow.
When sizing the new PSV do I take credit of the required or rated flow of the existing PSV ?
i.e. am I sizing the new PSV for 197,279 kg/h or 129,444 kg/h ?
I have an existing PSV installed at site sized for blocked outlet (required flow 364,536 kg/h / rated flow 432,371 kg/h).
The flow rate through my system is now increasing to 561,815 kg/h and hence we will add an additional smaller PSV to cover the extra flow.
When sizing the new PSV do I take credit of the required or rated flow of the existing PSV ?
i.e. am I sizing the new PSV for 197,279 kg/h or 129,444 kg/h ?