kodstruct
Structural
- Nov 9, 2012
- 27
Hi,
The contractor is having an issue on a project that I engineered and submitted an RFI.
Basically, he set the top of pier 6" lower than what is in the construction documents. Now the columns that the steel company shipped to the site are all 6" shorter.
They are asking if they can splice a piece of column to make up for the length. For me 6" doesn't meet the space/length for splicing. Any thought?
I was thinking about double plate splice with bolts. In other words, keep the base plate of the short columns, provide a plate at the top of the little stub column, bolt everything together.
Thanks.
The contractor is having an issue on a project that I engineered and submitted an RFI.
Basically, he set the top of pier 6" lower than what is in the construction documents. Now the columns that the steel company shipped to the site are all 6" shorter.
They are asking if they can splice a piece of column to make up for the length. For me 6" doesn't meet the space/length for splicing. Any thought?
I was thinking about double plate splice with bolts. In other words, keep the base plate of the short columns, provide a plate at the top of the little stub column, bolt everything together.
Thanks.