eski1
Mechanical
- Jun 15, 2004
- 90
Hi
we are planning to put a 14" sch 10 x 42m long pipe underground , it will be waste water going thru this to an effulent plant under gravity feed . my question is what type of welding join should we do , at present we are thinking of doing a butt weld full penetration & then weld a band over the top of this for extra strength. This would be to stop any potential future ground movement causing cracks in the weld etc . does anyone know the correct procedure ?
regards
chris
we are planning to put a 14" sch 10 x 42m long pipe underground , it will be waste water going thru this to an effulent plant under gravity feed . my question is what type of welding join should we do , at present we are thinking of doing a butt weld full penetration & then weld a band over the top of this for extra strength. This would be to stop any potential future ground movement causing cracks in the weld etc . does anyone know the correct procedure ?
regards
chris