Start and Stop of b31.1 and B31.3

Status
Not open for further replies.

QCPEEWEE

Structural
Aug 15, 2012
18
Good Morning All

I need help with clarification on Figure 100.1.2-3 in ASME B31.1-2018 pg 5.
I am bolting up a level radar transmitter past the double-block valves that come out of the steam drum on the boiler. I am being told due to the nipple we welded at the bottom of the housing had to be welded and tested according to ASME B31.1 due to it being bolted to the steam drum past the double-block valves. If I understand figure 100.1.2-3 that would be if this level bridal was to be welded in past the block vales. On the left side of the figure where it states multiple installations seems to be where this pertains to. If I read this correctly. See the pictures attached. I thank everyone in advance for all information.


IMG_0452_ux2yj5.jpg
IMG_0458_fyttyz.jpg
IMG_6537_rv0zan.jpg
IMG_20231205_221449_mhqv73.jpg
IMG_20231205_221451_zntslp.jpg
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor