thoughtofthis
Structural
- Jan 16, 2012
- 31
Steel roof and floor deck capacities are typically presented as a function of span condition. Most calculations I've seen assume a 3 span condition to get the most out of the deck; however, if you don't have supports in multiples of 4, wouldn't you be required to design some of the deck to a double or single span condition? When that is the case, how do you convey this in the contract documents?