I need to strengthening a existing 9" thick 2-way slab with new 5" topping slab on it to increase the slab capacity (to increase the "d" for bending and shear). We are going to short blast the existing slab and add a bonding agent and probably add some mechanical dowels. Is there any concerns we need to pay attention, for example the composite action between the new and old concrete, the shrinkage and cracking of the new topping slab, etc.The existing slab is 30 years old.
Thanks for any inputs.