Does anyone know the rough cost (range) of TEKLA 3D steel frame shop drawings for a say "standard" building (not very complex, rectangular grid, say 150,000 sqft)? Either per tonne or as a % of the steel contract. I have seen some claim the cost is 6-8% (even up to 10%) of the steel package contract, but this looks very high to me. Others have mentioned $60-$100 per tonne, which appears very low. Any help is much appreciated. Many thanks