Does anyone have experience in how long to erect the following tanks in Alberta?
80,000 bbl ------ 8 months?
40,000 bbl ------ 6 months?
25,000 bbl ------ 4 Months
20,000 bbl ------ 4 Months?
Your input is much appreciated.