CSFlanagan
Structural
My client is considering purchasing an existing 25,000 sf shell building. Building was constructed as a shell building by a local municipality. The building upfit was started by a prospective tenant, who then closed down. The building has never been used. The 4" thick floor slab has radiant heat below. Existing slab reinforcement is unknown. Soils in our area are dense clay and provide good bearing. The Under-slab radiant heat system is unknown, but these are typically placed on a stone sub-base, so it is reasonable to assume the sub-base of the slab was well compacted. Client does not intend to use the radiant heat.
My client wants to use the building for light storage, with forklifts (5000 pound capacity) and rack storage. Building eave is only 15 feet, so racks won't be too large or tall, and stored materials will be light.
Option 1 is to demo the floor slab and pour a new floor, probably 6" thick reinforced.
Option 2 is a topping slab, probably another 4" thick.
Option 3 is to use the floor as-is unless & until floor cracks become a problem. Then remove/replace as necessary.
CLient is only asking an opinion at this point. Concrete coring and subsurface investigation could be performed.
My client wants to use the building for light storage, with forklifts (5000 pound capacity) and rack storage. Building eave is only 15 feet, so racks won't be too large or tall, and stored materials will be light.
Option 1 is to demo the floor slab and pour a new floor, probably 6" thick reinforced.
Option 2 is a topping slab, probably another 4" thick.
Option 3 is to use the floor as-is unless & until floor cracks become a problem. Then remove/replace as necessary.
CLient is only asking an opinion at this point. Concrete coring and subsurface investigation could be performed.