PSEng01
Electrical
- Dec 22, 2019
- 9
New transformer usually go through soak test (as in no load) for a couple of hours before load is introduced. The tests that I have seen are energized from HV, leaving downstream LV switch open (of course, both HV and LV winding will be energized).
Recently there is a proposal from a contractor to perform this test twice, first energize from HV winding and second time is energizing from LV winding (as in, opening a HV breaker/switch somewhere).
I do not see the benefit of doing this test from LV end. Anyone else doing the same and have other thoughts?
Recently there is a proposal from a contractor to perform this test twice, first energize from HV winding and second time is energizing from LV winding (as in, opening a HV breaker/switch somewhere).
I do not see the benefit of doing this test from LV end. Anyone else doing the same and have other thoughts?