Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

traveling crane and monorail 3

Status
Not open for further replies.

0123654789

New member
Jul 26, 2009
29
good day every body,

this might be a stupid question: how to decide to use traveling crane or monorail for lifting? it seems traveling crane is much better than monorail as long as space is enough to put rails.

thanks for your reply!
 
Replies continue below

Recommended for you

Lifting ... what?
How often?



Mike Halloran
Pembroke Pines, FL, USA
 
I am sorry.

lifting equipment such as compressor, once per half year.

thanks for your asking.
 
Call a rigger, or rent a truck crane.



Mike Halloran
Pembroke Pines, FL, USA
 
thanks Mike.

I know mobile lifting equipment is always more economic than permanent one; however, this compressor is located inside building without large entrance.
 
If you have a single path where items need to be lifted and moved then a monorail will do the work much more economically. If there are multiple lifts which can't be set up on a single line of travel then you go to a bridge crane.

The simplest may be padeyes in the overhead and use chain falls and rig the equipment in and out of place.

The bridge crane adds maintenance requirements which may be excessive for infrequent lifts.
 
You can mount the compressor with a tripod and chain pulley block on a moving trolley. This trolley can then be dragged out. Alternately if a mobile crane with telescopic boom can be used,it makes life simpler. All these suggestions are made to avoid capital investments and occupying precious floor space .

Learn the rules,so you know how to break them properly.
Dalai Lama

_____________________________________
 
If the load is say under 5,000 lbs - temporary shoring or scaffolding with a monorail may do the trick..
 
Depending on the loads, having your rails / supports in place and then using a chain hoist or similar that you bring in for the semi annual lift can be effective. Be sure to have a qualified / licensed person review your loads and setup. They may be able to put a lifting plan together for you as well.

ZCP
 
Some plants install "I" beams above their large pumps and motors. They have an "I" beam trolley and a chain fall. If equipment is to be removed, the trolley is installed on the "I" beam and the chain fall used to lift the equipment. The "I" beam only need extend far enough to place the equipment on a a pallet jack or heavy duty cart. Even rollers may be used once the equipment is off the bed plate and on a flat floor.


Bill
--------------------
"Why not the best?"
Jimmy Carter
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor