I have a friend who decided to put holes thru the sides of his truss to run cabling thru and now he does not want to remove the cabling since it's installed. He's had a structural engineer look at it and the engineer told him to remove the cabling and scab the sides of the bottom chords with 4x4. I'm looking at scabbing the tops and bottoms of the bottom chord to allow the cables to remain in place. Thoughts or any other recommendations that I can give to the engineer to see if his calcs will work?