Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

two shops fabricating

Status
Not open for further replies.

engineer54

Mechanical
Jul 14, 2013
26

What paperwork/nameplate issues would there be if an ASME Section VIII div 1 vessel was fabricated up to hydro in one shop and sent to another shop to have paint and other finishing touches done. Both shops are company owned, one in Mexico , the finishing touches shop in the US.
 
Replies continue below

Recommended for you

When the vessel leaves the first shop, is the nameplate stamped and attached to the vessel?

Will any welding to the pressure boundary occur at the second shop?
 
No welding will be done at second shop. nameplate is installed when leaves first shop
finishing touches are sandblast, paint, and valve installation.
 
The vessel is essentially completed once the hydro test is performed and nameplate attached. The U Form would be prepared and certified at the shop where the vessel was manufactured.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor