johndeng
Structural
- Mar 6, 2012
- 120
I am checking a two way slab with 20 bays each way, each bay are 25'x25' with concrete beams 4 sides. Right now it has beams in column strip so it only used less than half of it's capacity. however the middle strip it only has one top bar #5@ 20", which is only less than half of the required capacity of the column strip. Will this work? It shifts all loads to column strip.
I remember I saw some PT slab before, they using bundled tendons in column strip while minimum steel reinforcement in middle strip.
Please advise. Thanks