Ultimate Time Not Reached 1

Status
Not open for further replies.

amt2013

Geotechnical
Aug 28, 2013
6
Hi,

I am currently running a case in Plaxis 2D of slope stability of unsaturated soils with rainfall. The period of case is 31 days with rainfall on the 6-13th and 27-29th days. I have managed to get completed results for consolidation but when I run for safety, the calculation stops on the 13th with ultimate time not reached. I have increased the additional steps to the maximum but the calculation still stops. Does anyone have any suggestions how I can continue the calculation process. I have included nil phase at the very beginning since I am using gravity loading in the initial phase. Thank you very much.
 
Replies continue below

Recommended for you

Have you tried go to manual setting on iterative procedures and change the maximum iterations ?
 
Thank you very much AndreBC for your reply. I have increased the iterations and it managed to continue calculating.
 