Smitash
Civil/Environmental
- Sep 20, 2012
- 17
Hi,
I have a problem..A contractor has not followed the structural plans and has cast 42 pad footings and columns.Now according to the load that the building will carry some of the foundations are found to be in adequate. Apart from demolishing and cast again, is there any method to remedy this?. Intermediate columns cannot be placed to reduce the loads spread.
Secondly, the Contractor should have placed ground beams. but the latter did not do that and has cast a 6m high column. According to the loading and height of the column, the reinforcement which the contractor has placed is not enough. Can the bars be dowel to place the ground beam?
I have a problem..A contractor has not followed the structural plans and has cast 42 pad footings and columns.Now according to the load that the building will carry some of the foundations are found to be in adequate. Apart from demolishing and cast again, is there any method to remedy this?. Intermediate columns cannot be placed to reduce the loads spread.
Secondly, the Contractor should have placed ground beams. but the latter did not do that and has cast a 6m high column. According to the loading and height of the column, the reinforcement which the contractor has placed is not enough. Can the bars be dowel to place the ground beam?