martin888888
Civil/Environmental
- Jun 15, 2010
- 157
I have an underground 8" DIP water line with another 8" process line running parralle 2.5' away at same CL EL. I want to place a MJ Tee on the waterline and then a 45 MJ Fitting to dive it under the proccess line. What is minimum length of pipe normally needed to fit between 2 MJ fittings and still use mechanical restraint glands (eg megalugs)? Just trying to see if the 2.5' seperation is to close to allow the waterline to be diverted underneath it.