bbookz
Structural
- Oct 19, 2005
- 27
I'm designing a two-story storage building (Like Extra Space Storage) about 320ft x 135ft. It's a walkout basement condition with grade differential between the long sides being 11'-4". I'm the foundation designer. The floor, roof, and above grade walls are a pre-engineered system; but essentially light gauge bearing walls 10ft o/c with composite deck for the floors and Z-purlins at 5ft o/c bearing on the same light gauge walls for the roof. I have not spoken to the pre-engineered system designer yet, but is is in there scope to design the lateral system which will likely consist a regularly spaced light framed shear walls or flat strap walls. We'll have to coordinate foundations for these items.
These things are built on the cheap. Typical interior bearing walls are supported on thickened slab foundations poured integral with the slab on grade (I don't really have a problem with this, but may have to do something different at hold lateral system downs). In an example project, they also stepped the side walls with grade (Properly designed as cantilevered retaining walls) so that the basement retaining wall stops below the floor level and has a light gauge knee wall between the top of concrete wall and upper level floor.
My question is if I consider surcharge (Passenger vehicles - I was going to use 100 psf, but maybe fire truck in an emergency), drainage is adequate and I properly design the wall as a cantilever are there any potential problems (maybe long term deflection or something) with saving wall concrete by stopping the wall short of the floor above on the sloped grade sides. I wasn't intending on designing the walls as a purely pin-pin basement walls anyway since there is unequal grade, its easy enough for the contractor to miss the note about not back filling the wall until the floor above is in place, and I would have to coordinate the top of wall connection with another engineer who is hard to get a hold of.
These things are built on the cheap. Typical interior bearing walls are supported on thickened slab foundations poured integral with the slab on grade (I don't really have a problem with this, but may have to do something different at hold lateral system downs). In an example project, they also stepped the side walls with grade (Properly designed as cantilevered retaining walls) so that the basement retaining wall stops below the floor level and has a light gauge knee wall between the top of concrete wall and upper level floor.
My question is if I consider surcharge (Passenger vehicles - I was going to use 100 psf, but maybe fire truck in an emergency), drainage is adequate and I properly design the wall as a cantilever are there any potential problems (maybe long term deflection or something) with saving wall concrete by stopping the wall short of the floor above on the sloped grade sides. I wasn't intending on designing the walls as a purely pin-pin basement walls anyway since there is unequal grade, its easy enough for the contractor to miss the note about not back filling the wall until the floor above is in place, and I would have to coordinate the top of wall connection with another engineer who is hard to get a hold of.