bridgebuster
Active member
- Jun 27, 1999
- 3,969
I need an opinion on a contractor’s proposed soldier pile and lagging scheme, see sketch. He’s rebuilding a bridge abutment in stages and can’t drive sheeting. The abutment isn’t very tall and sits on a mat foundation. The sheeting would have to go through the mat.
Toward the rear of the work area he wants to drive piles a few feet in and hold them with braces that would be wedged against the wingwall – I’m OK with the concept. However, near the front of the abutment he wants to drive two soldiers two feet below his demolition line and rely on two walers acting as cantilever beams to hold the piles in place.
In theory I see his point but I’m not convinced. I was thinking of stacking some mafia blocks on the "cantilever". It will interfere a bit with the formwork but they should be able to work around it.
Toward the rear of the work area he wants to drive piles a few feet in and hold them with braces that would be wedged against the wingwall – I’m OK with the concept. However, near the front of the abutment he wants to drive two soldiers two feet below his demolition line and rely on two walers acting as cantilever beams to hold the piles in place.
In theory I see his point but I’m not convinced. I was thinking of stacking some mafia blocks on the "cantilever". It will interfere a bit with the formwork but they should be able to work around it.