getitrightconcrete
Mechanical
- Feb 5, 2005
- 3
We are concerned about the work a concrete company has done. We learned halfway through the project that they should have been using a vibrator during the pours. We made them use one for the retaining walls, but they had already poured all the piers. The piers are 16' deep, 16" diameter. The cages are 4 vertical bars arranged in an 8.5" square with stirrups every 6". They did shake the top of the cages as the concrete neared the top, but I don't think it was doing too much. Should I be concerned or would the concrete been likely to flow well enough to prevent large voids?