I am coming onto a project with vertical post-tensioning designed as bonded post-tensioning, with grouted encasement.
The tendons have been installed and stressed, but there has been a delay of several months, and the ducts have still not been grouted.
They have been protected from weather, but I am trying to figure out if leaving the tendons stressed, but ungrouted, for a long period of time would lead to additional losses that would not have been seen otherwise?
Thanks so much in advance,
I am coming onto a project with vertical post-tensioning designed as bonded post-tensioning, with grouted encasement.
The tendons have been installed and stressed, but there has been a delay of several months, and the ducts have still not been grouted.
They have been protected from weather, but I am trying to figure out if leaving the tendons stressed, but ungrouted, for a long period of time would lead to additional losses that would not have been seen otherwise?