clarke1973
Structural
- Apr 21, 2014
- 70
Hello all,
I have four large warehouses to design - each 300m long x 90m wide x 15m high to eaves (5 deg roof slope). Construction will be standard lightweight steel clad frames. Large, uninterrupted internal spaces are required so I need to maximize internal column spacing. I am looking at different options for the roof framing, but will most likely be four-span frames (22.5m span) at say 7m centers along the length of the building. Transfer frames (truss or beams) supporting the main frames will span longitudinally between internal columns, giving a column spacing of 21m.
My question is regarding stability. Generally with this type of structure I would obviously portalise the frames, but I am thinking it may be more efficient to adopt a fully braced system, particularly given the height of the columns. The additional horizontal roof bracing would obviously be additional steel, but would it be offset by the saving in reduced perimeter column sizes and also the beam / column connections (pinned connections opposed to rigid)?
Obviously I can do some preliminary numbers for both options and do a tonnage / cost comparison, but does anyone here have any experience with structures of this size and can offer an opinion on the best approach?
Also, a number of areas will have large span cranes so horizontal deflection limits will need to be tighter than normal.
Thanks
I have four large warehouses to design - each 300m long x 90m wide x 15m high to eaves (5 deg roof slope). Construction will be standard lightweight steel clad frames. Large, uninterrupted internal spaces are required so I need to maximize internal column spacing. I am looking at different options for the roof framing, but will most likely be four-span frames (22.5m span) at say 7m centers along the length of the building. Transfer frames (truss or beams) supporting the main frames will span longitudinally between internal columns, giving a column spacing of 21m.
My question is regarding stability. Generally with this type of structure I would obviously portalise the frames, but I am thinking it may be more efficient to adopt a fully braced system, particularly given the height of the columns. The additional horizontal roof bracing would obviously be additional steel, but would it be offset by the saving in reduced perimeter column sizes and also the beam / column connections (pinned connections opposed to rigid)?
Obviously I can do some preliminary numbers for both options and do a tonnage / cost comparison, but does anyone here have any experience with structures of this size and can offer an opinion on the best approach?
Also, a number of areas will have large span cranes so horizontal deflection limits will need to be tighter than normal.
Thanks