I will use mobile crane to drop concrete to 2.6 m deep pile cap. My workers will vibrate each lift of 12" thick concrete with 6" inside lower lift of concrete.
My question is how many drum (0.7 cu.m/drum) should I drop before I need to start vibrate? Can I just fill out 12" thick of the pile cap or just start it from first drum? Is that any code define it?
Should I vibrate it till no more air bubble come out?
My question is how many drum (0.7 cu.m/drum) should I drop before I need to start vibrate? Can I just fill out 12" thick of the pile cap or just start it from first drum? Is that any code define it?
Should I vibrate it till no more air bubble come out?