SUSA12
Geotechnical
- May 18, 2012
- 2
I am involved with a small project in which vibratory stone columns were selected to improve the soils for support of shallow foundations. The soils consist of a silt (ML) in the upper 20 feet. (Avg N=5, M% - 22-28, DD = 95 pcf, no atterbergs were run). Below that the soils continue to be soft with increasing clay content. Water table at 12 feet (approx).
As the stone columns are installed the silty soils surrounding the stone columns become very soft. In several areas where multiple stone columns have been installed in close proximity water has been observed to bubble to the surface. Water has not come out of the stone column itself, but water could be seen in some of the stone columns a few feet from grade during installation. When standing on the ground next to the stone columns I can pump the ground about 6 inches. The contractor attempted to load test one of the VSC (3x3 ft on a 2ft dia VSC) after a couple days and had about 1.5 inches at 30 kips (not good). They let it sit another couple days and attempted to load it again and got about 0.5 inches at 20 kips. They also tested another stone column that had been in the ground for 3 days and got 3/4 inch of deflection at 20 kips.
The contractor has installed stone columns spread out across the site and has pulled off to give the pore water pressures time to dissipate and plan to do more testing next week. They tried to get a CPT cone out to measure pore water pressures, but the equipment was unavailable.
Has anyone seen these conditions? If so, how was it addressed.
As the stone columns are installed the silty soils surrounding the stone columns become very soft. In several areas where multiple stone columns have been installed in close proximity water has been observed to bubble to the surface. Water has not come out of the stone column itself, but water could be seen in some of the stone columns a few feet from grade during installation. When standing on the ground next to the stone columns I can pump the ground about 6 inches. The contractor attempted to load test one of the VSC (3x3 ft on a 2ft dia VSC) after a couple days and had about 1.5 inches at 30 kips (not good). They let it sit another couple days and attempted to load it again and got about 0.5 inches at 20 kips. They also tested another stone column that had been in the ground for 3 days and got 3/4 inch of deflection at 20 kips.
The contractor has installed stone columns spread out across the site and has pulled off to give the pore water pressures time to dissipate and plan to do more testing next week. They tried to get a CPT cone out to measure pore water pressures, but the equipment was unavailable.
Has anyone seen these conditions? If so, how was it addressed.