Triangled
Structural
- Jun 30, 2013
- 594
I have a double cantilevered glulam girder with 9' left cantilever and 9' right cantilever and 35.5' between columns for a total length of 53.5'
The moment diagrams for 3 cases (no snow) is attached, case 1 - TL everywhere, case 2 - TL at span (between columns) and DL only at cantilever (and roof supported by cantilever), case 3 - TL at cantilevers and DL only between columns.
My question is, what is proper length to use for Volume Effect Factor C[sub]V[/sub]?
The moment diagrams for 3 cases (no snow) is attached, case 1 - TL everywhere, case 2 - TL at span (between columns) and DL only at cantilever (and roof supported by cantilever), case 3 - TL at cantilevers and DL only between columns.
My question is, what is proper length to use for Volume Effect Factor C[sub]V[/sub]?