oengineer
Structural
- Apr 25, 2011
- 708
I have been tasked to design a 19' tall by 15.67' wide by 29' long equipment support structure (a Headworks structure). It has two levels. One is 12 ft then the other is 7 ft above that. It is supporting 3 equipment. Is drift due to wind typically considered for these designs? I come from an oil & gas background where we always considered drift for our structures using L/150. I am getting a drift of 3 inches in one of my columns at the top of the structure. Any suggestions/comments are helpful.
Also is there a recommended design for Water Resource Recovery Facility? Please let me know.