XFEM
Structural
- Nov 3, 2008
- 12
Hello, i am an new bridge design engineer. usually we design the welded wide flange in bridge truss and girder member as 100% capacity, and let the fabricator gave the member weld. Lately another fabricator asked about how it should be welded?
And i was said that should be CJP [Complete Joint Penetration] and the fabricator bargain about the fillet, and PJP, and PJP with extra fillet.
All welded beams are Wide Flange with fy 355 MPa.
Question mark 1: can my welded beam welded like that?
note: several beam use 8-10 thick web at stringers.
several beam use 12-14 thick web at crossgirders
many beams use 8-30 thick web at truss members
the tender code, i put was AWS D1.5
the fabricator usually use AWS D1.1
Question mark 2: I saw D1.5 today. It said the force tension pararel to weld efective can be PJP. It is for truss beam right? not for girder/stringer/
My opinion: I would like to bargain to fabricator:
The girder and stringer should be CJP.
The truss beam <= 19 mm thick web can be PJP with double beveled, others thicker should be CJP.
Right?
Note the process is SAW.
And i was said that should be CJP [Complete Joint Penetration] and the fabricator bargain about the fillet, and PJP, and PJP with extra fillet.
All welded beams are Wide Flange with fy 355 MPa.
Question mark 1: can my welded beam welded like that?
note: several beam use 8-10 thick web at stringers.
several beam use 12-14 thick web at crossgirders
many beams use 8-30 thick web at truss members
the tender code, i put was AWS D1.5
the fabricator usually use AWS D1.1
Question mark 2: I saw D1.5 today. It said the force tension pararel to weld efective can be PJP. It is for truss beam right? not for girder/stringer/
My opinion: I would like to bargain to fabricator:
The girder and stringer should be CJP.
The truss beam <= 19 mm thick web can be PJP with double beveled, others thicker should be CJP.
Right?
Note the process is SAW.