BCbrad
Industrial
- Dec 1, 2008
- 13
Hello,
I have a 32" OD Section VIII vessel where the Inlets and Outlets are NPS 10" and the Vents/Drain are NPS 3". Because of leak prevension we designed the nozzles to be welded to the piping system rather than use a flanged connection.
However the safety inspector is viewing the connection as an alteration to the vessel.
I thought that was some mention of this being acceptible in Section VIII, but I can not seem to locate it.
Does anyone have an idea where I can clarify, connecting the nozzles to the piping is either an alteration or it is acceptable?
Thanks
I have a 32" OD Section VIII vessel where the Inlets and Outlets are NPS 10" and the Vents/Drain are NPS 3". Because of leak prevension we designed the nozzles to be welded to the piping system rather than use a flanged connection.
However the safety inspector is viewing the connection as an alteration to the vessel.
I thought that was some mention of this being acceptible in Section VIII, but I can not seem to locate it.
Does anyone have an idea where I can clarify, connecting the nozzles to the piping is either an alteration or it is acceptable?
Thanks